Description of the total work on the project:
The construction of a combined cycle gas turbine CCGT unit with a capacity of up to 235 MW, consisting of:
- Four gas turbines LM 6000 PF DF Sprint production company "General Electric";
- Four steam boilers KGT-44/4,6-435-13/0,5-210;
- Two steam turbines of type T-17/23-4,5/0,18;
- Four modular booster compressor stations;
- Accessories
Work carried out by SYNERGETIC PROJECTS as General Contractor:
- Site preparation construction
- The construction of the Main construction projects and objects of auxiliary and service purpose including:
- The main building
- Oil emergency discharge tanks
- Construction of closed switchgear (indoor switchgear) 110 kV and 220 KV
- Installation of transformers
- Carcasona (circulation pump) and pumping production and fire water supply
- Cooling towers
- Chemical water purification
- The point of gas preparation
- Musahodjayeva
- Farm diesel fuel
- The modular compressor unit
- Warehouse of cylinders
- The water storage tanks 2х2400м3
- Pump station of foam extinguishing
- External technical and cable racks
- Permanent road
- External networks and constructions of water supply, sanitation, heating and gas supply
- Beautification and landscaping
- Temporary buildings and structures
- Conducting of pre-commissioning
Delivery by SYNERGETIC PROJECTS as a General Contractor
- Accessories, including but not limited to:
The equipment of the Main building - The outer part of the PSU
- Transformer pad
- ZRU
- Circulating pumping station, the pump is interlocked with the production-fire fighting water
- Booster pumping station domestic wastewater
- Pumping station industrial storm drains
- Sewage treatment plant
- Cooling tower
- WTP (water treatment plant)
- Storage of oil in containers
- Pumping diesel fuel
- Pumping pumping
- Compressor station
- Installation for the production of nitrogen