PHOTO_GTP_2012.06.23_Page_2_SMALL.jpg

A range of welding and assembly works on the pipelines of the gas treatment plant was carried out in the short time.

port_004.jpg

Over 15,000 pipe joints of a range of diameters from 15 to 1400 mm were welded. Installation of stainless steel pipelines was carried out. Assembly of the 120-ton gas air-cooling unit was performed. Assembly and installation of more than 500 tons of steel structures of pipe racks and service platforms were completed.

port_005.jpg

More than 1,000 fittings and valves were installed. Four types of testing of complete pipelines were carried out.